In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank – be certain to enter “0” wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 70 45 65 On-hand 30 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1 Q = L4L Gross requirements 70 45 65 Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases
https://d2vlcm61l7u1fs.cloudfront.net/media%2F37d%2F37d4edb0-6e3e-4578-a6d2-cc8795798ed7%2FphpZPDbHg.png
I have used orange color to for answers in the MRP schedule.
Red color has been used to highlight the given values.
Blue has been used to fill the empty cells.
Please rate quality of my answer 🙂